Legal Dismissal Over Contract Dispute

KOKO Business | People, Ideas, Markets, Growth | Legal Dismissal Over Contract Dispute

The court ruled that the Attorney General was not involved in the supply contract between the two companies, leading to the dismissal of the case against them.

The disagreement stemmed from materials provided for construction at Mulago Hospital, where Roko acted as the main contractor.

Roko initially ordered 2,398 steel door sets and related items in June 2017, valued at $1.57 million, with the quantity later increased to 2,716.

A separate order in January 2019 added ironmongery worth $365,342.97, raising the total value of supplies and installation to $2,581,667.58.

Assa Abloy stated that it delivered and installed the goods between 2017 and 2019, but Roko did not settle the remaining balance despite multiple requests.