KOKO Business · 3 Jan 2018
Power Outage Linked to Pipeline Shutdown

This action followed the Escravos pipeline shutdown, which disrupted gas supply to thermal plants.
The blackout affected several major power stations, including Egbin 1,320MW; Olorunsogo NIPP 676MW; Olorunsogo 338MW; Omotosho NIPP 450MW; Omotosho 338MW; and Paras 60MW.
Most Nigerian power generation relies on thermal plants that require gas, which is produced by oil and gas companies under the Ministry of Petroleum Resources.
NGPTC, a subsidiary of NNPC, owns and operates the pipelines delivering this gas to power stations.
Affected stations included Egbin 1,320MW; Olorunsogo NIPP 676MW; Olorunsogo 338MW; Omotosho NIPP 450MW; Omotosho 338MW; and Paras 60MW.
Thermal power plants, which generate most of Nigeria’s electricity, depend on gas supplied by oil and gas companies regulated by the Ministry of Petroleum Resources.
NGPTC, a subsidiary of NNPC, delivers this gas via pipelines critical for power station operations.