World Bank Warns of KSh168 Billion Compensation Delays on Isiolo-Mandera Road

KOKO Business | People, Ideas, Markets, Growth | World Bank Warns of KSh168 Billion Compensation Delays on Isiolo-Mandera Road

The World Bank has raised concerns over the delayed compensation for the KSh168 billion Isiolo-Mandera Road, which is affecting the progress of the 740-kilometre highway project. The bank has issued a warning to the Kenyan government, highlighting that the delays are causing the project to stall.

According to Qimiao Fan, the World Bank's Division Director for Kenya, Rwanda, Somalia, and Uganda, some sections of the road cannot proceed as planned due to contractors not having unrestricted access to the land. Fan noted that the bank had already released the funds, but compensation has not been made.

The World Bank estimates that every additional month of delays is costing the project approximately KSh1.2 billion. This highlights the financial impact of the compensation delays on the overall project timeline and budget.